Fusion Dental
Reston, Virginia
PROJECT INFORMATION
Liberty Construction was given an intense challenge to undertake by the Fusion Dental group for their new office in Reston VA. The project entailed building a 7000 square foot fully outfitted dental office with 24 operators in 90 days, in time for patients already scheduled for the 2021 summer. With a strict deadline, specifications from dental surgeons, and a large ground floor suite spanning across a concrete deck tensioned with PT cables, it took a tremendous amount of coordination between Liberty Construction, Patterson Dental and the building team at Penzance to make sure this project encountered no delays that could hinder the 3 month given to turn over the space to the doctors. We thank the Fusion Dental team for the opportunity to build one of the largest and fastest dental projects in our portfolio, and we’re excited to build more offices to expand their services to patients in the DMV area!